A block of flats with two entrances needs new aluminium balconies. The flats served by the first entrance have already been surveyed. At the second entrance, the owners have yet to agree on the façade works. Should the first group go ahead? Before making that decision, the property manager needs to know which balconies can be finished and handed over, what the second phase will still need from the first, and which costs the building would incur twice. The same question arises when all the flats are ready but one entrance must remain accessible throughout the works.
Start with a view of the building
Mark the entrances, the stacks of balconies and the side of the building on a photograph or elevation drawing. Add the routes residents take to the front doors, the pushchair store and the bins. Two entrances may share a footpath. Flats some distance apart in the corridor may have balconies above the same doorway. This simple drawing gives owners a better starting point for discussing the phases than a list of flat numbers alone.
Give each stack an unambiguous name
For the first meeting, a label such as “entrance A, courtyard side, left-hand stack as seen from the courtyard” will do. Use the same label in the enquiry, price breakdown and programme. Ask the contractor to confirm on site which balconies belong to that stack. Someone looking out from a flat and someone looking up from the courtyard can easily use “left” to mean opposite things. See what the company covers in its design, manufacture and installation of suspended balconies.
Where should phase one end?
Ask for a drawing showing what residents will see after the first installation team leaves. Which balconies will be complete? Which parts of the façade will still be unfinished? Which balcony doors will remain subject to access restrictions? If later work will take place above a finished section, the owners need to know how it will affect their use of it before they place the order. The contractor determines the work area and how it will be secured for the particular site.
An entrance and a work area can have different boundaries
Owners find it easy to identify their entrance. The designer and contractor may nevertheless propose working by elevation or by vertical stack. Ask them to point out the joint, edge or adjoining work that would remain unfinished if the phases followed the entrances. The manager can then give the residents who are waiting for their balconies a concrete reason for the proposed sequence.
What the two phases can share
Agree which drawings, finishes and railing panels the owners will approve for the whole building. If both entrances are to look alike, identify the approved sample and name the person who will keep it until the second batch is ordered. If the product changes or becomes unavailable, allow time for the manager to review a proposed substitute before manufacture. A photograph showing both the front and the sides of a completed balcony can help owners make their first selection.

The HS ALUSYSTEM project gallery records 32 suspended balconies, eight canopies and 32 pairs of side screens with drying racks at a building in Hlohovec. This is a useful example to take to a meeting. Dividing the number of balconies by two would tell the owners very little about the contents of each order. Each canopy belongs in a particular position. The photograph shows the completed building. It provides no information about the sequence in which these balconies were installed.
Compare one visit with two
Give each bidder the same marked-up drawing and ask for a price for a continuous installation and for the proposed split. Keep the total number of complete balconies, the extent of façade repairs and the agreed appearance the same in both cases. If one quote includes bringing lifting equipment to site twice and the other allows for a single visit, the difference between the totals tells you little about the price of an individual balcony.
Three lines to look for in the quote
- Work shared by both phases. Identify items priced once for the building. For the survey, ask whether a return visit to flats that were inaccessible the first time is included.
- Work specific to each phase. Assign the components to the relevant entrance or stack. Include canopies and side screens wherever they form part of the agreed supply.
- Work that must be repeated. Ask how the contractor will price return deliveries, bringing equipment back, securing the site again and restoring shared areas to the agreed condition.
If the second phase has no start date, record how long its price is valid and how a date will be confirmed. The guide to comparing balcony quotations covers other questions about the scope of the offer.
What has to be ready before each phase starts?
For each section, distinguish the information that releases the order for manufacture from the conditions needed for the team to start on site. Approving a railing design may settle one part of the order while the dimensions of one flat or the handover of a repaired façade surface are still outstanding. Give each open question a named contact and identify the balconies to which the answer applies.
When a date changes
If one stack has to wait, ask the contractor to confirm in writing whether work can proceed on another. Record any change to transport arrangements and identify the residents whose access restrictions will change. The balcony installation service describes the site work. The guide to briefing residents can help the manager turn the revised programme into a clear notice.
A decision involving a shared footpath
Imagine two entrances served by a single path from the street. The dimensions and railing panels at entrance A have been confirmed. Entrance B is waiting for façade work to be completed. Before agreeing to a first visit, the manager asks for a sketch of the route to each entrance during the works and the name of the person who will confirm when normal access can resume. The contractor also checks whether the second visit would require equipment to cross the reinstated area outside entrance A.
Two questions for the owners’ meeting
If entrance A goes first, when could its residents use their balconies, and what would change for them when the contractor returns? If both entrances wait, which repeat visits or operations could be avoided? Put the answers alongside the price of each option. The UK Health and Safety Executive explains the general principles of protecting the public around construction sites. The contractor will plan the actual access arrangements for your building.
Record a balcony moved to the later phase
If a flat is inaccessible, the team may be asked to move one balcony to the next phase. Give it the same identifier in the cost breakdown and programme. Record what has already been done, what remains and who confirmed that the change is feasible. When checking an interim invoice, the manager can then see whether an item already charged in part has been included at its full price in the second phase.
What to accept at the first entrance
Hand over by balcony position
Ask for a list of completed balcony positions with a date, any outstanding items and an explicit statement of which balconies may be used. Separately record the condition of the path, entrances and areas where the second phase will meet the first. If equipment will cross a reinstated area again, both parties can keep photographs of its condition at handover. After the last phase, bring the records together in the building’s balcony handover documents.
Questions from flat owners
Does each entrance need its own contract?
To compare bids, first define the scope, price and handover conditions of each phase. The owners can agree on the form of the order once they have chosen the scope and reviewed the offer.
Can the second batch be made with the first?
Ask whether the dimensions and finishes for that batch are final. If they are, agree where the parts will be stored, who will be responsible for them and how they will be accepted before installation at a later date.
What if the second phase has no firm date?
Distinguish the confirmed first visit from the provisional second phase in the quotation. Agree what needs to be checked again when the order is placed and who will tell owners the final price and date.
Can residents use a balcony once the railing is fitted?
Follow the confirmation issued for that flat. The manager should tell the resident whether the balcony has been handed over for use and whether any restrictions apply during the remaining work.
Send us your proposed phases
Contact HS ALUSYSTEM with a view of each side of the building, the entrances marked, the number of balconies and the reason you are considering separate phases. Include the remaining façade works and the routes residents use every day. At the first site visit, this gives everyone a basis for identifying where each phase should end and which items need separate prices.